Inver College - Co. Monaghan

Carrickmacross, Co. Monaghan

Total SQM: 825

Project Duration: 8 Months

Project Feature:

  • BER Rating: A
  • Low Carbon in Operation
  • Suspended Ceiling
  • Sensory Rooms
  • Modern Classrooms
  • Moveable Wheelchair Accessible Sink Units
  • In Built Elevator

The Task:

Asset Rentals received a enquiry from the Department of Education to manufacture & install a newly built modular building to spec. After conferring with both the DOE & the lead architects for the project at Inver College. Asset Rentals then received a task order to manufacture this school.

The Solution:

Asset first began tomanufacture the units while also

Commencing site works, including foundations for the units.

Asset Accommodation supplied Inver a Newly Built Modular Building.

Taking  8 months to have the units completely manufactured, installed & assembled.


The Asset Accommodation units were very well received by school management & DOE alike, they considered and spacious, elegant, and modern Teaching facility, which provided the pupils with modern, bright & accessible teaching space. Asset received praise from the client for our efficient, professional and

dedicated work in completing the project on time.